Storm Drain Inlet image

Current Storm drain projects include: 

424 Annual Storm Drain Improvements

  • Project Description:
    • This project is located at the intersection of Bard Street and Oak Street, which is located just north of Pier Avenue. The northern leg of the Bard Street and Oak Street intersection serves as the entrance to Marineland Mobile Home Park. The existing roadway and intersection configuration are prone to stormwater by-pass during heavy storm events, which overflows into the Marineland Mobile Home Park property. The purpose of the project is to construct new storm drain improvements at the intersection of Bard Street and Oak Street to intercept the stormwater to minimize overflows into the property. The proposed storm improvements include the construction of a new grated catch basin at the southwest corner of Bard Street and Oak Street that would connect to a new access hole and 91 linear feet of new storm drainpipe.

Construction start date: February 2025

Estimated construction end date: April 2025


422 Annual Storm Drain Improvements

  • Project Description: 
    •  This project will focus on addressing the current draining issue at this particular storm drain. The project includes the removal of an existing storm drain inlet at the corner of 5th Street and Ardmore Avenue, removal of existing storm drain piping and outlet structure, furnishing and installation of a new storm drain inlet, furnishing and installation of new storm drain piping, connection of storm drain piping to existing County of Los Angeles storm drain line, necessary demolition, excavation, and restorations.
  • Project Status:
    • Construction to begin September 30, 2024